Friday 30th Jan - Finish the story board.

Monday 2nd Feb - We are going to plan location, costumes, props.

Wednesday 4th Feb - Film in PP(Priory Park)until 5'oclock. Also buying props before hand.

Thursday 5th Feb - Filming again in PP all day after media and again until 5.

Friday 6th Feb - Last minute filming if needed/ upload the footage to the computer.

Saturday 7th Feb - Write up what we have done in the last two days of filming on Blogspot.

Monday 9th Feb - Put the shots in order on the computer and then beging cutting.

Thursday 12th Feb - Finishing cutting.

Friday 13th Feb - Create soundtrack(Tension music) whilst this is being done we will also continue cutting if not already finished.

Monday 23rd Feb - Doing the recording of'Dirty Little Secret' put TBP to the film and the 'tension' music.

Thursday 26th Feb - Put Dirty Little Secret music behind the film. Also tidy up the film and make sure that all is complete

Friday 27th Feb - Extra time if it is needed.